Golf course flood management work 2008-2009:. PHASE 2
PHASE 2 PROJECT
The second Phase of flood management work will start on 8th September 2008 and to be expected to run until the end of the year.This is the continuation from the first Phase that was successfully completed between December 07 and April 07, hence this will reduce the susceptibilty of the course to flood as well as improving its appearance.
THE WORKSCOPE:.
This will includes:.
- Raising the fairways of holes number 1,3,7 and 16 and,
- Creating new pond between hole number 3 and 7 as well as improving a number of the other ponds, are those at holes number 2,17 and 9/18
Below are the workplan timetable carrying out the project(s) and their estimated timing
| PROJECT | SCHEDULE DATE |
|---|---|
| raising the fairway hole 1 | 08th Sept 08 - 22nd Sept 08 |
| excavating pond between holes 7 &3 | 15th Sept 08 - 29th Sept 08 |
| raising fairway hole 3 | 22nd Sept - 06th Oct 08 |
| raising fairway hole 7 | 29th Sept 08 - 13th 0ct 08 |
| excavating pond hole 16 | 13th Oct 08 - 20th Oct 08 |
| drainage works hole 13,15 and 17 | 13th Oct 08 - 27th Oct 08 |
| raising fairway hole 16 | 13th Oct 08 - 27th Oct 08 |
| new pond hole 4 | 27th Oct 08 |
| miscellaneous drainage works | 27th Oct 08 - 24th Nov 08 |
| enlarging pond hole 8 | 03rd Nov 08 |
| enlarging pond hole 15 | 10th Nov 08 |
| pond holes 9 / 18 | 17th Nov 08 - 15th Dec 08 |
| line pond hole 17 | 24th Nov 08 - 01st Dec 08 |
| line pond hole 2 | 01st Dec 08 - 08th Dec 08 |
| new pond hole 5 | 15th Dec 08 |
| complete minor items | 22nd Dec 08 - 12th Jan 09 |
| reinstate damage | 12th Jan 09 - 19th Jan 09 |
timetable
The workplan planning has been formulated in order to minimise the disturbance to Panaga Golf Club members example by trying to carrying out as much of the fairway work as possible during the fasting month.
The flood management work will resulting in temporary restriction to some of the holes as the construction is still going on and all golfers are advised:.
- Not to enter the worksites and,
- Be mindful that the possibility of and where is required to keep a safe distance from heavy plant movement around the course for a safety purposes
Tree planting
A tree planting campaign has also been instigated with the objective of improving the visual definition of the holes. Specific thanks are due to Shell Deepwater, BSP’s SEN department, Laporpo golf society, Hardcore golf group, the Panaga Club secretary, Hjh Zaitun, and the forestry department for their support of the tree planting campaign.

1st tee box

Right side of 1st hole

Trees on the right of 8th hole

Trees on the right of 13th hole

Trees on the left of 17th hole
Nigel Snaith
PGC Vice Captain
To contact this section by email, go to the Panaga Club contacts page.